Performance Test of CBR(Chemical, Biological, Radiological) Protection Filtration Facility
Verification of CBR Protection Filtration Facility
Since the filtration system must supply air that is completely filtered from pollutants, it is necessary to verify the performance of the HVAC system by an independent and authorized testing agency and verify the inflow leakage.
– Absorber filter performance test
– On-site leak test of filtration equipment
– Positive pressure performance test
– Inflow leakage measuring test
– On-site Leak Test of HEPA Filter Purification System
less than 0.05% of challenge aerosols at ± 10% of rated flow rate
On-site leakage test of adsorbent filter unit: Test cycle less than 0.05% of tracking gas at ± 10% of rated flow rate: Every 12 months at the time of initial installation,
When the static pressure management standard of the filter unit is exceeded
– Absorber filter unit site leakage test
± 10% of rated flow rate and less than 0.05% of tracking gas
– Test cycle
At the time of initial installation or every 12 months, If the static pressure management standard of the filter unit is exceeded